Sorry for my absence!  I tell you about the release plan of 2.0.0.

# 2.0.0-rc1 (in a few days)

I plan to release 2.0.0-rc1 as soon as there is no "showstopper" issue.
Please report to me any showstopper if you know.
I consider the following type of issue as a showstopper.

   * a build failure (in major platforms),
   * a reproducible segfault (in normal use case),
   * a problem that significantly affects real/existing programs, or
   * a serious problem that has no workaround.

I'd like to release rc1 tomorrow night in JST if all showstoppers are
fixed (or if there is no report).


# 2.0.0-rc2 (in early Feb.)

You can freely commit any bug fixes (including non-showstopper issues)
until 2.0.0-rc2.

Note that I plan to prohibit any non-showstopper bug fixes after rc2
(to prevent regression).
In other words, you will be able to commit only showstopper fixes after rc2.
So, if you have any non-showstopper issue that you want to fix, you
must do it in this month.


# 2.0.0-p0 (at 24th Feb.)

Thanks!


しばらく不在にしてすみません。2.0.0 のリリースプランをご連絡します。

# 2.0.0-rc1 (数日以内)

"showstopper" な問題がなくなり次第 2.0.0-rc1 をリリースする予定です。
showstopper をご存知であれば申告してください。
以下のような問題を showstopper とみなします。

   * (メジャーな環境で) ビルドできない問題
   * (通常のユースケースでの) 再現可能な SEGV
   * 現実の・既存のプログラムに重大な影響を与える問題
   * 回避策のない重大な問題

showstopper がすべて修正されたら (または特に申告がなければ) 日本時間の明日の夜に
rc1 をリリースしたいと思います。


# 2.0.0-rc2 (2 月上旬)

2.0.0-rc2 までは任意のバグ修正を自由にコミットしてください (showstopper 以外も OK) 。

regression を防ぐため、rc2 以降は showstopper 以外のバグ修正を禁止する予定です。
つまり、rc2 以降は showstopper の修正のみがコミット可能です。
よって、showstopper 以外で修正したい問題があれば、今月中にやってください。


# 2.0.0-p0 (2/24)

よろしくお願いします!


2012/12/27 SASADA Koichi <ko1 / atdot.net>:
> (English only)
>
> (I post this message as a substitute of Endo-san, release manager of
> Ruby 2.0.0. He is very busy now)
>
> Thank you for your help.
> Now, Ruby 2.0.0 (trunk) is "code freeze" status.
>
> We want to emphasize the following two things.
>
> (1) Bug fix only
>
> Only bug fixes are acceptable before RC2 (beginning of Feb).
>
> Do *not* add any new features.
> If you need to add new features or spec changes to solve an issue,
> please get my (Endo-san's) approval.
>
>
> (2) Identify showstoppers
>
>> ## Identifying showstoppers: ASAP
>>
>> I will identify "showstoppers" among 300+ bug tickets.  They will be
>> marked by the immediate priority.  A "showstopper" means:
>>
>>   * a reproducible segfault,
>>   * a problem that significantly affects real/existing programs, or
>>   * a serious problem that has no workaround.
>>
>> We will identify bug tickets that are reported after the identifying,
>> as needed.
>
> If you find any *critical* issues as showstoppers, please tell us ASAP.
>
>
> Thank you.
>
>
> (2012/12/03 1:00), Yusuke Endoh wrote:
>> ALL COMMITTERS SHOULD READ THIS MAIL! コミッタはこのメール読んで!
>> ALL COMMITTERS SHOULD READ THIS MAIL! コミッタはこのメール読んで!
>> ALL COMMITTERS SHOULD READ THIS MAIL! コミッタはこのメール読んで!
>>
>> Japanese follows; 日本語は後で
>>
>> I tell you the plan for 2.0.0 release.
>> Please let me know if you have any idea about the plan, especially,
>> if you think that there is a problem in the plan.
>>
>> ## Milestones
>>
>>   - Identifying showstoppers: ASAP
>>   - code freeze: 23 Dec.
>>   - 2.0.0-rc1 release: the first week of Jan. (expected)
>>   - 2.0.0-rc2 release: the first week of Feb. (expected)
>>   - 2.0.0-p0 release: 24 Feb.
>>
>>
>> ## Identifying showstoppers: ASAP
>>
>> I will identify "showstoppers" among 300+ bug tickets.  They will be
>> marked by the immediate priority.  A "showstopper" means:
>>
>>   * a reproducible segfault,
>>   * a problem that significantly affects real/existing programs, or
>>   * a serious problem that has no workaround.
>>
>> We will identify bug tickets that are reported after the identifying,
>> as needed.
>>
>>
>> ## Code freeze: 23 Dec.
>>
>> Or, feature implementation deadline.  2.0.0 will NOT include the
>> (even accepted) new features that are not implemented by this
>> deadline.
>>
>>
>> ## 2.0.0-rc1 release: the first week of Jan. (expected)
>>
>> After all showstoppers are resolved, we will release 2.0.0-rc1.
>> (It may be late depending on the status.)
>>
>> I'll determine "platform support level" based on whether rc1 works
>> properly on the platform or not.
>> After 2.0.0-rc1, we will try to resolve non-showstopper bug tickets
>> as many as possible.
>>
>>
>> ## 2.0.0-rc2 release: the first week of Feb. (expected)
>>
>> After we resolve showstoppers that are reported after rc1, we
>> will release 2.0.0-rc2.
>>
>> I'd like to create a new branch ruby_2_0 at this time.
>>
>> After 2.0.0-rc2, we will try to resolve only showstoppers reported
>> after rc2.  In principle, we will NOT resolve non-showstoppers to
>> avoid a regression.
>>
>>
>> ## 2.0.0-p0 release: 24 Feb.
>>
>> PARTY!
>>
>>
>>
>> 2.0.0 リリースの予定をお伝えします。
>> この予定に関して何か意見があれば (特に問題があると思う場合は) ぜひ
>> 教えてください。
>>
>> ## イベント
>>
>>   - showstopper の同定: なるべく早めに
>>   - コードフリーズ: 12/23
>>   - 2.0.0-rc1 リリース: 1 月第一週目標
>>   - 2.0.0-rc2 リリース: 2 月第一週目標
>>   - 2.0.0-p0 リリース: 2/24
>>
>>
>> ## showstopper の同定: なるべく早めに
>>
>> 300 件あまりあるバグチケットから showstopper を同定します (優先度を
>> Immediate にします) 。showstopper とは以下を指します。
>>
>>   * 再現性のある SEGV
>>   * 実世界の、または既存のプログラムに重大な影響を与える問題
>>   * 回避策がない重大な問題
>>
>> その後報告されたバグチケットは随時判断します。
>>
>>
>> ## コードフリーズ: 12/23
>>
>> 新機能実装締め切りです。この締め切りまでに実装されなかった新機能は
>> (たとえ accept されているものでも) 2.0.0 に含まれません。
>>
>>
>> ## 2.0.0-rc1 リリース: 1 月第一週目標
>>
>> すべての showstopper が解消されたら、2.0.0-rc1 を出します。
>> (進捗次第で遅れるかもしれません)
>>
>> rc1 の動作実績を元に platform support level を決めようと思います。
>> 2.0.0-rc1 の後は、showstopper でないバグチケットを出来るだけ解決
>> するよう努力します。
>>
>>
>> ## 2.0.0-rc2 リリース: 2 月第一週目標
>>
>> rc1 の後で報告された showstopper を解決した後で、2.0.0-rc2 を
>> リリースします。
>>
>> この時に ruby_2_0 のブランチを作りたいと思います。
>>
>> 2.0.0-rc2 の後では、rc2 後に報告された showstopper のみ解決します。
>> regression を避けるため、原則として、showstopper でない問題の修正は
>> 行いません。
>>
>>
>> ## 2.0.0-p0 release: 2/24
>>
>> パーティー!
>>
>
>
> --
> // SASADA Koichi at atdot dot net
>



-- 
Yusuke Endoh <mame / tsg.ne.jp>