On May 9, 2011, at 08:43 , Yuki Sonoda (Yugui) wrote: > -----BEGIN PGP SIGNED MESSAGE----- > Hash: SHA1 >=20 > Hi, >=20 > First of all, I am sorry for proposing a plan to Ruby 1.9.3 so late. > I missed proposing it because of the earthquake in Japan. >=20 > Now Ruby 1.9.3 is much stable than on Feb. Its feature is getting > stable. It's time to decide a plan to release Ruby 1.9.3. >=20 > I propose the following rough schedule. > * The end of May: feature freeze. create ruby_1_9_3 branch. > * The end of Jan: implementation freeze. don't change without > permission after that. > * The end of Jul or early Aug: release Ruby 1.9.3 I'm a bit confused. I'm assuming that "Jan" should be "Jun" for the impl = freeze. Is that correct? If so, we're talking about releasing 1.9.3 = July/August of 2011. There is going to be stuff for rubygems that we won't have done until = the end of June due to personal schedules and timing.